ANZCIP - Bringing Profitable Manufacturing Back to Australia

Pre-feasibility status

  • Financials - Evaluated [internal]

  • Stress Test - Conducted in PFS. Positive.

  • Commercials - Counter parties identified

  • Sales - Distribution channel Identified

  • Market demand - Assessed

  • Manufacturing - Motor manufacturing partners identified.

  • Automation - Technology, Vendors identified

  • FEED, EPC - Design, Construction partners identified

Project Timeline

PFS Validate                 2027 Q1

DFS Generate               2027 Q2-Q4

FEED                                2028 Q1-Q2

Financial Close           2028 Q3

Construction [EPC]   2028 Q4 – 2030 Q2

Operations                   2030 Q3 onwards

Project Timeline

Next Steps…

Step 1 – Confirm PFS:

Pre-feasibility study is 80% complete. Confirmation and independent validation  (Commercial, Technical, Financial) of Pre-feasibility Study.

Step 2 – DFS, FEED, Financial Close:

Conduct Independent Detailed Bankable Feasibility Study. Generate FEED. Facilitate and expedite Equity, Debt, and negotiations to financial signoff